Rousselot Gelatinas do Brasil / Nordika - Production Area Expansion / Amparo - SP. Steel Structure Design Development and Construction Documents for Tower Dryer;

Pharlab Indústria Farmacêutica SA / SPL Engenharia - New Production Area / Lagoa da Prata - MG. Steel Structure Design Development and Construction Documents for Roof and Pipe Rack.

Cogumelos Yuri - Administrative Building and Cold Chamber / Sorocaba - SP. Structure Schematic Design, Design Development and Construction Documents for entire building;

2017

GRU Airport / Engecorps - São Paulo International Airport - Passenger Terminal 3 Expansion / Guarulhos - SP. Steel Structure Design Development and Construction Documents for roof and facades of departure area and boarding pre-bridges;

2016

American Airlines / FSB - Frankfurt Short Bruza / Envision PM – Maintenance Hangar for two Boeing 777-300 ER - Wide Body Maintenance Hangar / Guarulhos - SP. Steel Structure Construction Documents for Hangar, Workshops and Pipe Rack;

Latam Airlines / KTY / Engecorps - Maintenance Hangar for Boeing 777-300 ER - Wide Body Maintenace Hangar / Guarulhos - SP. Steel Structure Construction Documents for Hangar, Workshops, Warehouse and Support Buildings.

  

GRU Airport / TPS2 / Engecorps – Boarding Bridges / Guarulhos - SP. Steel Structure Design Development and Steel Structure Construction Documents for Passenger Boarding Bridges;

 

2015

GL Events – Exhibition Hall - Expo São Paulo / Imigrantes, São Paulo - SP. Steel Structure Design for Exhibition Hall Roof, Workshop Building, Canopy and Lateral Enclosure Support Structure for Parking Building;

 

METRÔ - Companhia do Metropolitano de São Paulo / Geodata / Infra 7 - Brooklin, Moema and Eucaliptos Stations - Line 5 / São Paulo - SP. Steel Structure Construction Documents for Main Entrance Roof and Ventilation Grills;

 

2014

METRÔ - Companhia do Metropolitano de São Paulo / Intertechne - EBEI - Dutra Station - Line 2 - Green / São Paulo - SP. Steel Structure Design Development for Access A, Access B, Access C, Operational Room Roof, Technical Room Roof and Bus Terminal Roof;

 

Carrefour Property Divison - Shopping Jardim Pamplona / São Paulo - SP. Steel Structure Design Development for Repurposing of Existing Building with change of use – Supermarket to Shopping Center;

 

​ Merial Saúde Animal / SPL Engenharia – Production Building and Warehouse Expansion / Paulínia - SP. Steel Structure Construction Documents for Roof and Mezzanine;

 

2013

Viracopos Aeroportos Brasil / Consórcio Construtor Viracopos / Intertechne - Viracopos International Airport / Campinas - SP. Steel Structure Construction Documents for Lateral Enclosures – Pier A, B, C and Interlink Corridor-, Visitor Deck, Emergency Stairs and Secondary Structures for Parking Building;

 

VALE / Metso Minerals – Northern Logistic Training - Ponta da Madeira Terminal / São Luis - MA. Steel Structure Calculation for Transfer Towers CT-315K-201, CT-315K-202 and CT-315K-203;

 

John Deere - Tractor Factory Expansion / Montenegro - RS. Steel Structure Construction Documents;

 

​Unilever Brasil - HC and PC Pilot Plant / Valinhos - SP. Steel Structure Design Development for Roof, Mezzanine and Technical Floor;

 

2012

​Petrobras / Galvão Engenharia / Projectus - KTY - REPLAN - Refinaria de Paulínia - Diesel Plant / Paulínia - SP. Steel Structural Calculation for Compressor Building;

 

​Petrobras / CNEC WorleyParsons / Skanska - UTE Baixada Fluminense – Power Generation / Seropédica - RJ. Steel Structure Construction Documents for Main Pipe Rack, Secondary Pipe Rack, ETA Pipe Rack, TGG Pipe Rack, Cable Rack, Circuit Breaker Platform, Pump House, Compressor House, Administrative Building, Electrical Building, Workshop Building, Warehouse and TGV Control Building;

 

2011

​Petrobras / CNEC WorleyParsons - RPBC - Refinaria Presidente Bernardes - Diesel Plant / Cubatão - SP. Steel Structure Construction Documents for Pipe Rack and Cable Rack;

 

​Petrobras / Graneísa Equipamentos - COMPERJ - Complexo Petroquímico do Rio de Janeiro / Itaboraí -RJ. Steel Structure Calculation for: Silo with 120 m3 capacity for petroleum green coke - Unity U-6821 - Courtyard Handling / Coke Storage ; Belt Conveyors MM6821 1001/1002/1003/1004/1005 and 1006 - Unity U-6821 - Courtyard Handling / Coke Storage; Transfer Towers CT-01, CT-02, CT-03 and CT-04 - Unity U-6821 - Courtyard Handling / Coke Storage;

 

​METRÔ - Companhia do Metropolitano de São Paulo / Intertechne -  14 Bis,  Higienópolis Station and João Paulo Terminal - Line 6 - Orange / São Paulo - SP. Steel Structure Design Development for Station Access and Terminal;

 

2010

​Hyundai Motor Brazil / ETALP – Automotive Industry / Piracicaba - SP. Steel Structure Construction Documents for Main Structures, Roofs, Lateral Enclosures, Platforms, Stairs, Crane Bridges, Secondary Structures and Pipe Rack;

 

​Petrobras / Consórcio TEAG -Techint - Andrade Gutierrez - COMPERJ - Complexo Petroquímico do Rio de Janeiro / Itaboraí - RJ. Steel Structure Construction Documents for: Loading Yard Building - Unity U-6821 - Courtyard Handling / Coke Storage; Canvas Building - Unity U-6821 - Courtyard Handling / Coke Storage; Yard Control Building - Unity U-6821 - Courtyard Handling / Coke Storage; Coke Sample Preparation Room - Unity U-6821 - Courtyard Handling / Coke Storage; SE-6821 Substation Building - Unity U-6821 - Courtyard Handling / Coke Storage; Compressor Building - Unit U-2200 – Retarded Coking Unit; SE-2200 - Unit U-2200 – Retarded Coking Unit;

 

2009

​Governo do Estado do Mato Grosso - Arena Pantanal / Cuiabá - MT. Steel Structure Design Development for Lateral Enclosures, Canopies, Press Room Mezzanine, Technical Mezzanine and Electronic Scoreboard Support;

 

2008

Associação Guarulhense – Steel Sculpture by the Artist Tomie Ohtake in honor of the Centenary of Japanese Immigration / Guarulhos - SP. Calculation and Design;

 

CSN / IESA - Mineração Casa de Pedra - 53 MT Expansion - Stocking, Shipment and Wagon Loading / Congonhas - MG. Structural Calculation for Iron Ore Handling Equipment: Double Boom Stacker - 26-EP-20; Rotating Boom Stacker 32-EP-201 / 32-EP-202; Fixed Boom Stacker 41-3724; Wheel on Boom Reclaimer 32-RT-201 / 32-RT-202; Bridge Reclaimer - 26-RT-201;

 

VALE / Metso Minerals - Complexo de Tubarão – Pelletizing Plant VIII – Ore Feeding / Vitória - ES. Structural Calculation for Belt Conveyor Structures, Stretching Towers, Transfer Towers for Belt Conveyors TR- 811- 01, TR-811- 02, TR-811- 03, TR-811- 04, TR-811- 06, TR-812- 02, TR-812- 03 and TR- 813;

 

John Deere – Parts Distribution Center / Campinas - SP. Structural Verification for Existing Roof and Support Detailed Design for the Installation of the sprinkler systems.

 

Petrobras / Bardella Indústrias Mecânicas - REPLAN - Refinaria de Paulínia – Second Coke Handling Yard / Paulínia - SP. Structural Calculation of: Tilting Boom Stacker EP- 9850 for petroleum green coke with 167 t/h nominal capacity and 200 t/h project capacity; Portal Scrapper RM -98501 for petroleum green coke, with 300 t/h nominal capacity and 360 t/h project capacity;

 

​Foz do Chapecó Energia S/A / CNEC Engenharia – Hydroelectric Plant Foz do Chapecó / Águas de Chapecó - SC. Steel Structure Construction Documents for Power House, Water Catchment, Spillway and Forced Conduit;

 

2007

Valeo Sistemas Automotivos – Administrative Building, Warehouse, Entrance and Restaurant - Itatiba SP. Steel Structure Design and Steel Structure Construction Documents for Roofs, Enclosures, Canopies and Pipe Rack;

 

URBAM - Urbanizadora Municipal S/A – Bus Terminal Frederico Ozanan / São José dos Campos -SP.  Steel Structure Construction Documents for Suburban Terminal Roof and Canopy and Service Building Roof;

 

MRN - Mineração Rio do Norte / Metso Minerals -Trombetas Fase IV - 16,3 MT Expansion - Porto Trombetas / Oriximiná - PA. Structural Calculation for: Tilting Stacker  EP-223-01 and  Double Fixed Boom Stacker  EP-248-02;

 

CSN / Metso Minerals - Porto de Sepetiba -TECAR – Ore Storage Yard - Ilha da Madeira / Itaguaí -  RJ. Structural Calculation for Transfer Towers TT-01, TT-02, TT-03, TT-05, TT-06 and Downloading Tower;

 

CBA - Companhia Brasileira de Alumínio / Bardella S/A Indústrias Mecânicas S/A – Double Boom Stacker EMP-01-02, with 961 t/h capacity / Miraí - MG. Structural Calculation; ​

 

Consórcio Empresarial Salto Pilão / CNEC Engenharia - Hydroelectric Plant Salto Pilão / Lontras - SC. Steel Structure Construction Documents for Power House Crane Bridge;

 

​ Petrobras / CNEC Engenharia / Skanska / Camargo Corrêa - UTE Cubatão – Power Generation  / Cubatão - SP. Steel Structure Construction Documents for East-West Pipe Rack, North-South Pipe Rack and Derivation, HSRG Deaerator Structure, Auxiliary Deaerator Structure, Turbo Steam Generator Building, Steam Conditioning Valves Platform, Workshop Building, Warehouse and Laboratory; 

 

2006

​Petrobras / CNEC Engenharia / Projectus - UTE Três Lagoas – Power Generation / Três Lagoas - MS. Steel Structure Construction Documents for Workshop and Warehouse Building Expansion;

 

Usiminas - Usinas Siderúrgicas de Minas Gerais S/A / CNEC Engenharia / Camargo Corrêa - Gas and Fuel System – Thermoelectric Plant 2 / Ipatinga - MG. Steel Structure Construction Documents for: Pipe Rack, Electric Boiler Room, Electric Water Demineralization Room, Demineralized Water Treatment System, Boiler Oil Pump House, Cooling Tower Electric Room, Compressed Air Tank Platform, Turbo Generator Operating Platform, Turbo Generator Building;

 

Petrobras / CNEC Engenharia / Camargo Corrêa – Thermoelectric Plant Termoaçu – Thermal Power Cogeneration Plant / Vale do Açu, Alto do Rodrigues - RN. Steel Structure Construction Documents for Pipe Rack, Crane Bridge, Support Structure for - Crane Bridge, Circuit Breaker, Cooling Water Tank and Pump House Roof;

 

2005

CST- Companhia Siderúrgica de Tubarão / Consórcio - Marubeni Corporation / Steel Plantec / Dedini / Siemens - Continuous Casting Machine 3 / Vitória - ES. Steel Structure Construction Documents for: Steel Ladle Receiving Building, Tundish Maintenance Building, Run Out Building, Mold & Segments Building, Chemical Storage Building, Restaurant, Utilities and Recirculation Water Building, Casting Platform, Main Pulpit, Cutter Pulpit, Caster Tower and Pipe Rack;

 

Valeo Wipers  Systems – Production Building, Laboratory, Waste, Restaurant, Main Gate and Inspection Gate / Campinas - SP. Steel Structure Construction Documents; ​

 

Petrobras / CNEC Engenharia - UTE Canoas – Power Generation / Canoas - RS. Steel Structure Construction Documents for Pipe Rack;

 

2004

CST- Companhia Siderúrgica de Tubarão / Metso Minerals – Mining Yard - 7 MT Expansion Plan / Vitória - ES. Structural Calculation for: Silo, Storage Hopper, Screen Tower, Transfer Tower and Metal Extractor Tower;

 

Valeo Security System – Production Building, Administrative, Main Gate, Energy Cabin, Chemical Products Storage Building  and Pipe Rack / Guarulhos - SP. Steel Structure Construction Documents for Main Structure, Secondary Structures, Roofs and Enclosures;

 

Novo Nordisk / SPL Engenharia - Filling Plant - Common, Filling, Packaging, Storage, Energy Center, Utilities Buildings and Interlink Footbridge / Montes Claros - MG. Steel Structure Construction Documents for Roofs, Canopies, Stairs, Secondary Structures and Pipe Rack;

 

​Usiminas - Usinas Siderúrgicas de Mina Gerais S/A / Bardella Indústrias Mecânicas. Structural Calculation for Iron Ore Stacker / Reclaimer with 900 t/h stacking capacity and 750 t/h recover capacity;

 

2003

Secretaria Municipal de Abastecimento / Consórcio Paulistano - OAS, JZ Engenharia e EBOTE - São Paulo Municipal Market – Reform and Requalification Project. Steel Structure Construction Document for Mezzanine;

 

Mineração Serra do Sossego / Metso Minerals – Ship Loader 8051-CN-01 / São Luis - MA. Structural Calculation for Rotating Ship Loader with Tilting and Telescopic Boom, for Concentrated Copper;

 

CST - Companhia Siderúrgica de Tubarão / Metso Minerals  - 7,5MT Plan – Minerals, Pellets and Sintering / Vitória - ES. Transfer Tower and Screen Tower Structural Calculation;

 

CVRD - Companhia Vale do Rio Doce / Metso Minerals – Weighing and Sampling Station – Maritime Terminal Ponta da Madeira / São Luis - MA. T-17A Transfer Tower Structural Calculation;

 

​Petrobras / Bardella Indústrias Mecânicas - REDUC - Refinaria Duque de Caxias – Coke Storage Yard / Duque de Caxias - RJ. Structural Calculation for: Tilting Boom Stacker EP- 410001, for petroleum green coke, with 250 t/h nominal capacity and 275 t/h project capacity and Portal Reclaimer RM-410001, for petroleum green coke, with 525 t/h nominal capacity and 577 t/h project capacity;

 

2002

CVRD - Companhia Vale do Rio Doce / Metso Minerals - Complex Mining of Carajás - N5 Mine Crushing System / Carajás - PA. Structural Calculation for Semi-Mobile Crushing System III (BSM III) Transfer Tower TR-117K-07;

 

CVRD - Companhia Vale do Rio Doce / Metso Minerals – Pelletizing Plant – Limestone Milling / Vitória - ES. Structural Calculation for: Transfer Tower CT-TR-TC-06/07, Limestone Silo and Silo Support Structure;

 

Carbones Del Caribe / Metso Minerals - Project Rio Córdoba / Córdoba - Colombia. Structural Calculation for Double Stayed Boom Tripper for Coal;

 

Cia Mineradora Disputada de Las Condes / Metso Minerals – Scoria Treatment Project / Santiago - Chile. Structural Calculation for Belt Conveyor CT-4110-2052;

 

Prefeitura Municipal de Barueri / Satio Tomita Arquitetura – Barueri Municipal Stadium / Barueri - SP. Steel Structure Design Development for Stadium Covering;

 

2001

Alunorte - Alumínio do Norte do Brasil S/A / Svedala – Bauxite Storage / Barcarena - PA. Structural Calculation for Stacker E-1B-1 Tripper;

 

MRN - Mineração Rio do Norte S/A / Svedala - Porto Trombetas - Fase IV - 16,3 MTPA Expansion / Oriximiná - PA. Structural Calculation for: Bauxite Stacker EP-220-01 Tripper and Trailer; Bauxite Stacker EP-223-01; Equalizer Beam for Bauxite Wheel on Boom Reclaimer RCC-220-01 / RCC-28-02 / RCC-284-03;

 

CVRD - Companhia Vale do Rio Doce / Confab Industrial / Techint - Italimpianti / Elfa Engenharia - Ferro Carajás Project – Second Screen Station / São Luis - MA. Structural Calculation for: Transfer Towers CT-312K21, CT-312K-22; Structures for Belt Conveyor TR-312K-21, TR-312K-22 e TR-312K-23;

 

CVRD - Companhia Vale do Rio Doce / Confab Industrial / Techint - Italimpianti / Elfa Engenharia - Ferro Carajás Project – Storage Yard C & D - Mine / Carajás - PA. Load at Foundation Calculation for Belt Conveyor TR-315K-26;

 

Termonorte Energia / CNEC Engenharia / Hyundai Construction Brazil / Camargo Corrêa -Termonorte Phase II Power Plant Project / Porto Velho - RO. Steel Structure Construction Documents for Pipe Rack and Secondary Structures;

 

​Shopping Porto Itaguá / GCP Arquitetos / Shopping - Ubatuba - SP. Steel Structure Construction Documents for Main Structure, Roof and Façades;

 

1995 - 2000

​Kraft Lacta Suchard Brasil S/A / SPL Engenharia – Food Industry  / Curitiba - PR. Steel Structure Construction Documents for Pipe Rack, Canopies and Escape Route Footbridge;

 

Prodome Química e Farmacêutica / SPL Engenharia - Investiment Plan - Fase I / Campinas - SP. Steel Structure Construction Documents for Pipe Rack and Interconnection Walkway between Production Buildings;

 

Intervias / MK Engenharia  - Toll Station - Highways - State of São Paulo. Steel Structure Construction Documents for de Araras, Descalvado, Iracemápolis, Leme, Limeira, Mogi Mirim, Rio Claro and Santa Cruz Toll Stations;

 

SPVias / MK Engenharia – Toll Station – Highways – State of São Paulo. Steel Structure Construction Documents for Alambari, Avaré, Buri, Gramado, Iaras, Morro Alto and Quadra Toll Stations;

 

CVRD-Companhia Vale do Rio Doce / Metso Minerals  - Yard J / Carajás - PA. Structural Calculation for Transfer Tower TR-A2B/T12/C2A/B3G;

 

Sar Cheshmeh Copper Mining Company / Svedala - Appron Feeder Support / Iran. Structural Calculation for Apron Feeder Support;

 

Cia Suzano de Papel e Celulose KBR / Kellog Brown & Root / Promon Engenharia - Machine 8 – Fiber Recovery System / Suzano - SP. Steel Structure Construction Documents for Machine 8 Platform;

 

Ultrafértil / Odebrecht / Icolmaq Equipamentos / Tecnowood Engenharia / Elfa Engenharia – TUF Optmization and Upgrading / Cubatão - SP. Structural Calculation for Transfer Towers, Fertilizer and Sulphur Belt Conveyor Structures, Crossings and Pipe Rack; 

 

GM - General Motors Brazil / Engevix  - Sand Receiving and Transportation  / São José dos Campos - SP. Steel Structure Construction Documents for Sand Receiving Building;

 

CPTM - Companhia Paulista de Trens Metropolitanos - Patio Capão Redondo / Andrade Gutierrez / Maubertec Engenharia / São Paulo SP. Steel Structure Construction Documents for Roof and Enclosures of the Buildings A, C, D, E, F e H; 

 

Laboratórios Pfizer / EBEPRO – Administrative Headquarters - São Paulo SP. Steel Structure Construction Documents for Façades in Wing Shape;

 

CPTM - Companhia Paulista de Trens Metropolitanos / ATC Engenharia e Sistemas – Train Stations / São Paulo - SP. Steel Structure Construction Documents for Access Building, Boarding Platform and Interconnection Footbridge for Morumbi, Granja Julieta, Hebraica Rebouças Stations;

 

CVRD - Companhia Vale do Rio Doce / Svedala – Fertilizer Terminal / Vitória - ES. Structural Calculation for Mobile Hopper AM;

 

​MRN - Mineração Rio do Norte S/A / Svedala - Porto Trombetas - Fase III / Oriximiná - PA. Structural Calculation for Bauxite Stacker EP-224-01;